Grupos >
ESTRUCTURAS EN HORMIGON ARMADO >
En :
APU de Zapatas de H.A. fc= 280 kg/cm2
En :
1. MATERIALES | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 9.00 | 7.68 | 69.12 |
15977 | Tabla dura de encofrado de 0.30 m. | u | 3.03 | 5.50 | 16.67 |
16101 | Alambre galvanizado No.18 | Kg | 2.00 | 2.54 | 5.08 |
16137 | Varilla corrugada 8-10-12 mm | 1.50 | 40.11 | 60.17 | |
16138 | Varilla corrugada 14mm o mayor | 1.50 | 40.11 | 60.17 | |
18054 | Arena | m3 | 0.58 | 13.50 | 7.83 |
18055 | Ripio | m3 | 0.71 | 18.00 | 12.78 |
18056 | Agua | m3 | 0.26 | 0.85 | 0.22 |
18912 | Cuartones de encofrado | u | 4.55 | 4.00 | 18.20 |
18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 2.40 | 2.13 | 5.11 |
19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.02 | 22.60 | 0.45 |
Total materiales | 255.79 |
2. MANO DE OBRA | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15837 | Peón | Hora | 13.45 | 4.05 | 54.47 |
15843 | Fierrero | Hora | 6.73 | 4.10 | 27.59 |
15844 | Carpintero | Hora | 13.45 | 4.10 | 55.15 |
15868 | Maestro de Obra | Hora | 6.73 | 4.33 | 29.14 |
Total mano de obra | 166.35 |
3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
18057 | Concretera 1 saco | Hora | 0.57 | 4.48 | 2.55 |
18058 | Vibrador de manguera | Hora | 1.14 | 4.06 | 4.63 |
Herramientas menores % | 5.00% | 8.32 | |||
Total equipo, maquinaria y herramientas | 15.50 |
4. GASTOS GENERALES Y ADMINISTRATIVOS |
5. UTILIDAD |
6. IMPUESTOS | ||
Total Precio Unitario de Zapatas de H.A. fc= 280 kg/cm2 | 437.64 |
Especificaciones técnicas:
RENDIMIENTO: 2.60 Horas/m3