Grupos >
ESTRUCTURAS EN HORMIGON ARMADO >
En :
APU de Vigas de amarre Cubierta H.A. fc= 280 kg/cm2
En :
1. MATERIALES | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 9.00 | 7.68 | 69.12 |
15977 | Tabla dura de encofrado de 0.30 m. | u | 11.12 | 5.50 | 61.16 |
16096 | Alambre galvanizado No.18 | Kg | 2.27 | 2.54 | 5.77 |
16137 | Varilla corrugada 8-10-12 mm | 2.22 | 40.11 | 89.04 | |
16138 | Varilla corrugada 14mm o mayor | 1.67 | 40.11 | 66.98 | |
18054 | Arena | m3 | 0.58 | 13.50 | 7.83 |
18055 | Ripio | m3 | 0.72 | 18.00 | 12.96 |
18056 | Agua | m3 | 0.28 | 0.85 | 0.24 |
18912 | Cuartones de encofrado | u | 3.33 | 4.00 | 13.32 |
18913 | Tiras de encofrado | u | 5.00 | 1.88 | 9.41 |
18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 3.78 | 2.13 | 8.04 |
19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.02 | 22.60 | 0.45 |
19961 | Caña Rollisa 6 metros | u | 17.50 | 2.25 | 39.38 |
Total materiales | 383.70 |
2. MANO DE OBRA | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15837 | Peón | Hora | 16.59 | 4.05 | 67.19 |
15838 | Albañil | Hora | 2.37 | ||
15843 | Fierrero | Hora | 2.37 | 4.10 | 9.72 |
15844 | Carpintero | Hora | 2.37 | 4.10 | 9.72 |
15868 | Maestro de Obra | Hora | 2.37 | 4.33 | 10.26 |
Total mano de obra | 96.89 |
3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
18057 | Concretera 1 saco | Hora | 2.37 | 4.48 | 10.62 |
18058 | Vibrador de manguera | Hora | 2.37 | 4.06 | 9.62 |
Herramientas menores % | 5.00% | 4.84 | |||
Total equipo, maquinaria y herramientas | 25.08 |
4. GASTOS GENERALES Y ADMINISTRATIVOS |
5. UTILIDAD |
6. IMPUESTOS | ||
Total Precio Unitario de Vigas de amarre Cubierta H.A. fc= 280 kg/cm2 | 505.67 |
Especificaciones técnicas:
RENDIMIENTO: 2.37 Horas/m3