APU de Losa de H.A. fc= 280 kg/cm2
En :
1. MATERIALES | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 9.00 | 7.68 | 69.12 |
15977 | Tabla dura de encofrado de 0.30 m. | u | 0.51 | 5.50 | 2.81 |
16101 | Alambre galvanizado No.18 | Kg | 1.15 | 2.54 | 2.92 |
16137 | Varilla corrugada 8-10-12 mm | 1.04 | 40.11 | 41.71 | |
16138 | Varilla corrugada 14mm o mayor | 2.37 | 40.11 | 95.06 | |
18054 | Arena | m3 | 0.58 | 13.50 | 7.83 |
18055 | Ripio | m3 | 0.73 | 18.00 | 13.14 |
18056 | Agua | m3 | 0.25 | 0.85 | 0.21 |
18912 | Cuartones de encofrado | u | 0.55 | 4.00 | 2.20 |
18913 | Tiras de encofrado | u | 1.05 | 1.88 | 1.98 |
18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 0.29 | 2.13 | 0.62 |
19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.02 | 22.60 | 0.45 |
19747 | Varilla Lisa 5.5 mm x 5.90 m - Andec DISENSA | u | 5.48 | 1.40 | 7.67 |
Total materiales | 245.72 |
2. MANO DE OBRA | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15837 | Peón | Hora | 18.34 | 4.05 | 74.28 |
15838 | Albañil | Hora | 2.62 | ||
15843 | Fierrero | Hora | 2.62 | 4.10 | 10.74 |
15844 | Carpintero | Hora | 2.62 | 4.10 | 10.74 |
15868 | Maestro de Obra | Hora | 2.62 | 4.33 | 11.34 |
Total mano de obra | 107.11 |
3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
18057 | Concretera 1 saco | Hora | 2.62 | 4.48 | 11.74 |
18058 | Vibrador de manguera | Hora | 2.62 | 4.06 | 10.64 |
Herramientas menores % | 5.00% | 5.36 | |||
Total equipo, maquinaria y herramientas | 27.73 |
4. GASTOS GENERALES Y ADMINISTRATIVOS |
5. UTILIDAD |
6. IMPUESTOS | ||
Total Precio Unitario de Losa de H.A. fc= 280 kg/cm2 | 380.56 |
Especificaciones técnicas:
RENDIMIENTO: 2.62 Horas/m3